How Long Does a Kitchen Remodel Take on the Peninsula?

A mid-range kitchen remodel usually takes 2 to 3 months from first design meeting to a working kitchen, and about 6 weeks of that is construction. Here is the timeline for a refresh, a mid-range and a high-end kitchen.

Aziz Construction · Published · Updated · 3 min read

The short answer

A mid-range kitchen remodel on the Peninsula usually takes 2 to 3 months from the first design meeting to a working kitchen, and about 6 weeks of that is construction. A simple refresh can be built in 3 to 5 weeks. A high-end remodel with custom cabinetry or layout changes takes 3 to 5 months of construction alone.

These are typical timelines for Palo Alto and the Peninsula, not a schedule for your home. Your timeline is set at consultation and depends on the job.

Kitchen remodel timeline by level

PhaseRefreshMid-rangeHigh-end
Design and selections1 to 2 weeks2 to 3 weeks6 to 10 weeks
Permit0 to 2 weeks1 to 2 weeks2 to 6 weeks
Construction3 to 5 weeksAbout 6 weeks3 to 5 months

A refresh keeps the same layout with new or refaced cabinets, counters, sink, faucet, lighting and paint. A mid-range remodel adds semi-custom cabinets, stone counters, new appliances and minor layout changes. A high-end remodel adds custom cabinetry, professional appliances or structural changes such as removing a wall.

Cabinet and appliance lead times

Custom cabinets and special-order appliances can add 8 to 12 weeks of lead time. We order them during design, so construction starts once permits, final selections and materials are ready, and the kitchen is not torn out while you wait for deliveries.

What makes a kitchen remodel take longer?

  • Moving the sink, range or gas line, or removing a wall, which can need structural engineering and a longer permit review.
  • Professional ranges that need new gas lines and range hood ductwork.
  • An electrical panel upgrade for induction cooking or more circuits.
  • Older homes with hidden problems behind the walls.
  • Selections still open when demolition starts.

Keeping the existing layout and plumbing locations, and making every selection before demolition, are the two surest ways to keep a kitchen on schedule.

What does a kitchen remodel cost?

Construction of a kitchen remodel in Palo Alto and the Peninsula typically costs $38,000 to $72,000 for a refresh, $80,000 to $145,000 for a mid-range full remodel and $140,000 to $260,000 or more for a high-end remodel. Design and permit fees are extra; city permit fees for a typical kitchen run about $1,500 to $2,500. See the kitchen cost guide for the full breakdown.

Living at home during the remodel

If you stay in the house, plan where you will cook, wash dishes and keep the refrigerator for the weeks of construction, and agree on access, deliveries and pets with the project team before work starts. Include any temporary living costs in your planning budget, even though they sit outside the construction contract.

Kitchen timeline FAQ

How long does a mid-range kitchen remodel take? Usually 2 to 3 months from the first design meeting to a working kitchen, including about 6 weeks of construction.

How long does a high-end kitchen remodel take? Plan on 6 to 10 weeks of design and selections, 2 to 6 weeks for the permit and 3 to 5 months of construction.

How long is a kitchen without a working sink or stove? For a mid-range remodel, about the 6 weeks of construction. A refresh is usually 3 to 5 weeks, and a high-end remodel 3 to 5 months.

Do custom cabinets delay a kitchen remodel? Custom cabinets and special-order appliances can take 8 to 12 weeks to arrive. Ordering them during design keeps that wait out of the construction schedule.