How Long Does It Take to Build an ADU in the Bay Area?

A detached ADU usually takes 8 to 14 months from first design meeting to move-in, and a garage conversion or junior ADU 5 to 8 months. Here is where the time goes and what slows it down.

Aziz Construction · Published · Updated · 4 min read

The short answer

A detached ADU in the Bay Area usually takes 8 to 14 months from the first design meeting to move-in. A garage conversion or junior ADU (JADU) is usually done in 5 to 8 months. About two to five months of that is design and city review; the rest is construction.

These are typical timelines for the Peninsula and South Bay, not a schedule for your property. Your timeline is set at consultation and depends on the site, the city and the scope.

ADU timeline by phase

PhaseTypical time
Design and engineering6 to 10 weeks
City permit review4 to 8 weeks in San Jose; 6 to 12 weeks in Palo Alto
Construction, junior ADU2 to 4 months
Construction, garage conversion3 to 5 months
Construction, attached ADU5 to 8 months
Construction, detached ADU6 to 10 months

Construction starts once the permit is issued. Design and review run one after the other, so a complete first submission saves more time than anything done later.

How long does city permit review take?

In Palo Alto, plan on 6 to 12 weeks of city review for an ADU. In San Jose it is usually 4 to 8 weeks. Other cities on the Peninsula and in the South Bay vary, so confirm the current review process with the city that covers your address.

California law requires a city to approve or deny a complete ADU application within 60 days. The clock starts only when the application is complete, so missing documents or a second round of corrections can push the real time past 60 days. See HCD's ADU resources for the state rules.

What causes ADU delays?

The three biggest causes of delay we see are:

  • Incomplete plans: a submission that needs a second round of city review can add weeks before the permit is issued.
  • PG&E scheduling: a new meter, panel upgrade or service change depends on PG&E's schedule, not just the builder's.
  • Changes after construction starts: moving walls, fixtures or finishes once work is under way means rework, new orders and sometimes revised plans.

Site conditions add time too: long utility runs from the street, sloped lots, retaining walls and trees the city protects all need extra design or review work.

How to keep an ADU on schedule

  • Gather your property information early: existing plans, permit history and photos help the design team avoid surprises.
  • Make finish selections during design, so nothing waits on orders once construction starts.
  • Ask for a complete permit set the first time, including the engineering and Title 24 energy report the city needs.
  • Start the utility conversation early if the ADU needs its own meter or a panel upgrade.
  • Choose a simpler scope where it fits your goals: converting a garage or existing space is usually faster than building new.

What does an ADU cost while you wait?

Construction of an ADU on the Peninsula and in the South Bay typically costs from $125,000 for a simple garage conversion to $550,000 for a two-bedroom detached unit, roughly $325 to $650 per square foot. Design, permits and utility fees are extra. See the ADU cost guide for prices by ADU type.

ADU timeline FAQ

How long does a garage conversion ADU take? A garage conversion is usually done in 5 to 8 months from the first design meeting, including 3 to 5 months of construction.

How long does it take to build a detached ADU? A detached ADU usually takes 8 to 14 months from first design meeting to move-in, with 6 to 10 months of that in construction.

How long does ADU permit review take in Palo Alto? Plan on 6 to 12 weeks of city review in Palo Alto. In San Jose it is usually 4 to 8 weeks. California law requires a decision within 60 days of a complete application.

What delays an ADU the most? Incomplete plans that need a second round of city review, PG&E scheduling for meters and panel upgrades, and changes made after construction starts.

Sources

State rules: HCD ADU information. Palo Alto: official Palo Alto ADU resource. Resources checked October 30, 2026. The timelines on this page are typical figures for the Peninsula and South Bay, not a schedule for your property.