Aziz Construction is a licensed general contractor (CSLB #1103807) based in nearby Palo Alto. We build detached ADUs, attached ADUs, garage conversions and junior ADUs for homeowners in our selected Atherton service area. A detached ADU typically costs $260,000 to $550,000 to build and takes 8 to 14 months from the first design meeting to move-in.
The ADUs we build in Atherton
- Detached ADU: a freestanding home on the lot. The Town’s ADU brochure allows an ADU of up to 1,200 square feet.
- Attached ADU: connected to the main home by at least one wall, with its own entrance on the side or rear where feasible.
- Converted ADU: built within existing space or the footprint of an existing permitted accessory structure, such as a garage. It needs side and rear setbacks sufficient for safety and its own front door.
- Junior ADU: up to 500 square feet, contained entirely within the house, with an efficiency kitchen and a separate or shared bathroom.
Compare the options in our garage conversion versus detached ADU guide.
What an ADU costs to build in Atherton
An ADU in Atherton and across the Peninsula typically costs $125,000 for a simple garage conversion up to $550,000 for a two-bedroom detached unit, or roughly $325 to $650 per square foot. These are construction costs: labor and materials, including standard finishes. Custom finishes, long utility runs and tree protection push a project toward the top of the range or beyond it.
| ADU type | Typical size | Construction cost |
|---|---|---|
| Junior ADU (JADU), inside the house | 250 to 500 sq ft | $75,000 to $150,000 |
| Garage conversion | 350 to 450 sq ft | $125,000 to $215,000 |
| Attached ADU | 500 to 800 sq ft | $235,000 to $400,000 |
| Detached ADU, 1 bedroom | 450 to 650 sq ft | $260,000 to $400,000 |
| Detached ADU, 2 bedrooms | 700 to 1,000 sq ft | $360,000 to $550,000 |
Budget separately for design, engineering and the Title 24 energy report, typically $10,000 to $35,000. The Town has waived a number of its own permit fees for ADUs, but outside agencies charge their own permit and service fees: the Menlo Park Fire Protection District, CalWater and, depending on the property, Fair Oaks Sanitary or West Bay Sanitary (Town of Atherton ADU page). The application also needs a school district notice that impact fees are paid or waived. These are typical ranges, not a quote; your exact price is quoted at consultation. See what moves the price in our ADU cost and timeline guide.
What Atherton asks for with an ADU permit
Atherton’s ADU process page lists the documents a complete application needs. Plans are filed through the Town’s Building ePlan submittal portal, and a complete application includes:
- Site plan: setbacks from property lines, structures and trees.
- Construction, Operations and Parking plan: how construction access, operations and parking will be handled on the property.
- Tree protection plan: protection has to be installed and inspected before the permit is issued.
- Geotechnical report: or a soils report waiver request.
- Outside approvals: a Menlo Park Fire Protection District approval letter and a school district notice that impact fees are paid or waived.
- Business licenses: the general contractor needs a Town business license before the permit is issued, and each subcontractor before final inspection.
Grading, landscape screening and water-efficient landscaping plans can need separate submittals. We gather these with the drawings so the first submission is complete.
How long an Atherton ADU takes
A detached ADU usually takes 8 to 14 months from the first design meeting to move-in, and a garage conversion or junior ADU 5 to 8 months. Design, the Town’s site documents and outside agency approvals come first; construction starts once the permit is issued.
| Phase | Typical time |
|---|---|
| Design and engineering | 6 to 10 weeks |
| Town permit review | State law requires a decision within 60 days of a complete application |
| Construction, junior ADU | 2 to 4 months |
| Construction, garage conversion | 3 to 5 months |
| Construction, attached ADU | 5 to 8 months |
| Construction, detached ADU | 6 to 10 months |
The fire district letter and tree protection inspection run alongside plan review, so we start them early. Read more in how long it takes to build an ADU.
What we handle, from design to move-in
One team manages your ADU, so you have one point of contact through the build:
- Feasibility and scope: your lot, the unit type and how the ADU will be used.
- Design coordination and engineering: drawings, structural engineering and the Title 24 energy report.
- Permit support: the Town submission and responses to plan-check comments.
- Construction: site preparation, foundation, framing, roofing, plumbing, electrical and HVAC.
- Finishes, inspections and completion: interior finishes, Town inspections and handover.
Read more about our ADU construction service.
Atherton ADU rules to check first
- Current standards: ADUs are governed by Chapter 17.52 of the Atherton Municipal Code, last updated in March 2024. Amendments for the 2024 and 2025 state ADU laws went to the City Council in November 2025, so we confirm the current height, setback and parking standards with the Planning Department before design (Town ADU page).
- Parking: the Town’s brochure says most ADUs need one parking space, reachable from the street and screened from it; tandem parking on an existing driveway may qualify.
- Pre-approved plans: designers can have ADU plans approved by the Town, which then lists them, and the Town points to the San Mateo County ADU Resource Center’s pre-approved designs (Town building ADU page).
- Unpermitted units: the Town’s ADU Amnesty Program, open through January 1, 2030, can legalize an ADU that existed before January 1, 2020.
The lot shapes the rest. In Atherton’s main residential district, the main house is limited to a floor area of 18% of the lot and sits at least 60 feet from the front and rear lot lines (Municipal Code 17.32.040); the ADU chapter sets the ADU’s own limits. Mature trees, driveway access for construction and the sewer district that serves the property all affect where an ADU can go and what the site work costs. See our Atherton remodeling and construction page for other Town resources.
Atherton ADU questions
Do you build ADUs in Atherton?
How much does it cost to build an ADU in Atherton?
How big can an ADU be in Atherton?
Does Atherton have pre-approved ADU plans?
What does Atherton need with an ADU permit application?
Can I legalize an existing unpermitted ADU in Atherton?
How long does it take to build an ADU in Atherton?
ADU construction in nearby cities
We also build ADUs in Palo Alto, Menlo Park, Los Altos and Mountain View. See all service areas.
Town rules on this page come from the Town of Atherton’s own pages, brochure and municipal code, as checked on November 17, 2026. Atherton is updating its ADU rules; use the current Town guidance for your property.